Skip to content

American Concrete Institute (ACI) FTT

Question 1 of 67

1% Complete
00:00Time Elapsed
1Single Choice

According to ASTM C143, after the final lift of concrete is rodded, the concrete pile is struck off with a tamping rod using a sawing and rolling motion. What is the next required step before lifting the slump cone?

Reveal the answer to continue